People

Worth 33% of the PMI PMP (PMP) exam. CertClue has 174 questions on this objective.

What this objective covers

Conflict Resolution Techniques Compared

Every PM eventually faces conflict among team members or stakeholders, and PMI exams expect you to match the situation described to the one conflict-handling technique that fits best, not just to define the terms.

Exam tip. If a scenario shows the PM making a unilateral, fast decision under a safety or compliance emergency, the answer is force/direct, not collaborate, even though collaborate is usually the best-outcome answer on the exam.

Stakeholder Analysis Tools at a Glance

PMI expects you to distinguish between several similarly named stakeholder tools; each classifies or documents stakeholders along different dimensions, and picking the wrong one is a common exam trap.

Exam tip. If a question mentions legitimacy or urgency as a classification factor, the answer is the salience model, not the power-interest grid, which only uses power and interest.

Practice questions

Free, with the answer and the reasoning. No account needed.

1. A project manager increases team members' base salaries and improves their office equipment, expecting this to significantly boost motivation and engagement. According to Herzberg's two-factor theory, what is the most likely outcome?

  • A. Motivation will increase substantially and remain elevated, since pay and equipment are the primary drivers of long-term engagement.
  • B. These changes have no effect at all on the team's satisfaction or performance.
  • C. These changes will decrease motivation because higher pay creates unhealthy competition among team members.
  • D. These changes address hygiene factors, which can prevent dissatisfaction but are unlikely by themselves to create lasting motivation, since true motivation comes from factors like achievement, recognition, and meaningful work.correct

In Herzberg's two-factor theory, salary and working conditions are hygiene factors, their absence causes dissatisfaction but their presence does not, by itself, create lasting motivation, which instead comes from motivator factors such as achievement, recognition, responsibility, and meaningful work. Expecting substantial, lasting motivation from pay and equipment alone misapplies the theory, since hygiene factors only prevent dissatisfaction rather than driving engagement. Claiming no effect at all overstates the case, since these changes can still prevent active dissatisfaction. Assuming higher pay creates unhealthy competition is not what the theory predicts and is not supported by the scenario.

2. Two senior developers on a hybrid delivery team disagree strongly over the technical design for a critical module, and the disagreement is starting to affect team morale ahead of a demo. There is still time before the demo. What should the project manager do FIRST?

  • A. Escalate the disagreement to the sponsor and let them decide the technical approach
  • B. Facilitate a joint problem solving session between the two developers to reach a mutually agreeable solutioncorrect
  • C. Assign each developer to a separate module so they no longer need to interact
  • D. Direct the team to use the approach the project manager personally believes is correct

With adequate time and a strong working relationship worth preserving, collaborate or problem solve is generally the strongest conflict resolution technique because it produces a win win outcome both parties can support. Escalating to the sponsor is premature since this is a team level technical disagreement, not something outside the project manager's authority. Separating the developers avoids the conflict rather than resolving it. Directing the team to a single approach without discussion is forcing, which can resolve the immediate issue quickly but tends to breed resentment and does not use the strongest available option.

3. Which of the following is the clearest EARLY warning sign of team disengagement that a project manager should watch for?

  • A. Declining participation in team discussions and reduced volunteering for new taskscorrect
  • B. A team member taking previously scheduled vacation time
  • C. A team member asking clarifying questions during planning sessions
  • D. A team member requesting formal training on a new tool

A noticeable decline in participation and a drop off in volunteering for new work are classic early indicators that a team member is disengaging, often before more serious problems appear. Taking previously scheduled vacation time is a normal, planned event with no connection to disengagement. Asking clarifying questions during planning is a sign of engagement and thoroughness, not withdrawal. Requesting formal training reflects continued investment in growth and capability, which runs counter to disengagement.

Work the whole objective

The full PMI PMP bank, the study notes behind these summaries, and a readiness score that tells you which objective to revise next. Free, no paid tier.

Take the free PMI PMP practice test

The other PMI PMP objectives