Conflict Resolution Techniques Compared
Every PM eventually faces conflict among team members or stakeholders, and PMI exams expect you to match the situation described to the one conflict-handling technique that fits best, not just to define the terms.
Exam tip. If a scenario shows the PM making a unilateral, fast decision under a safety or compliance emergency, the answer is force/direct, not collaborate, even though collaborate is usually the best-outcome answer on the exam.
Stakeholder Analysis Tools at a Glance
PMI expects you to distinguish between several similarly named stakeholder tools; each classifies or documents stakeholders along different dimensions, and picking the wrong one is a common exam trap.
Exam tip. If a question mentions legitimacy or urgency as a classification factor, the answer is the salience model, not the power-interest grid, which only uses power and interest.
Choosing a Leadership Style for the Situation
PMP questions rarely ask which leadership style is best. They describe a team and a moment, and ask which style fits. The answer turns on two things: how capable the team is at this particular task, and how committed they are to it. A team that has done the work ten times needs delegation; the same team facing an unfamiliar technology needs direction, and offering delegation there reads as abandonment.
Exam tip. When a stem says the team is experienced, any answer where the project manager assigns detailed tasks is wrong, even if it sounds diligent.
What To Do First When a Conflict Surfaces
Conflict questions almost always offer one answer that resolves the conflict, one that escalates it, one that avoids it and one that gathers information. The PMP position is that the project manager addresses conflict directly and early, at the lowest level, in private, and treats it as a team issue rather than a personality issue. Escalation is a later step, not a first one.
Exam tip. Answers containing remove the team member, tell the sponsor immediately or let them work it out are almost always distractors.
Communication Planning That Survives Contact With Stakeholders
A communications plan answers who needs what information, when, in what form and from whom. The two failures the exam tests are sending everyone everything, which trains people to ignore you, and relying on push communication for anything that needs agreement. The third, less obvious, is failing to confirm that the message was understood rather than merely delivered.
Exam tip. If a stem describes a misunderstanding after a status report was sent, the fix is interactive communication, not a better report.